Yamazumi Chart: How to Balance Work with a Manufacturing Example

A yamazumi chart, also called an operator balance chart, stacks the work elements assigned to each operator or station. The height of each bar shows its total work content. A takt-time line helps a team see where an allocation exceeds the required production pace.
The chart is most useful when its colored segments represent work that the team can examine and, where practical, reassign. This guide uses a fictional automotive component assembly to explain how to create the chart and test a revised balance.
- What a yamazumi chart shows
- How to create a yamazumi chart
- 1. Set the product scope and takt time
- 2. Define work elements that can be discussed
- 3. Record comparable times
- 4. Stack the elements and add the takt line
- 5. Make a revised allocation and test it
- Worked example: moving a six-second recording task
- Creating the chart in Excel
- Checking line balance numerically
- Common questions about yamazumi charts
- Should all bars be exactly the same height?
- Is this the same as a standard work combination sheet?
- Summary: balance the real work, then verify the method
- Analyze work content before balancing with Ollo Factory
What a yamazumi chart shows
A typical chart has operators or stations on the horizontal axis and seconds per unit on the vertical axis. Each segment represents an element such as checking a part, setting a fixture, fastening, inspection or recording.
The chart helps answer three questions:
Which assignments exceed takt or have little margin for variation?
What work makes up each assignment?
Which elements could move without creating another problem?
The highest bar is a candidate for investigation, not conclusive proof of the system bottleneck. Material shortages, equipment downtime or a shared inspection resource may constrain actual output elsewhere.
How to create a yamazumi chart
1. Set the product scope and takt time
Choose a product or family with a meaningful common method. Calculate takt as net available production time divided by required quantity for the same period. Keep conditions that differ substantially, such as different variants or shifts, visible rather than combining them into an unexplained average.
2. Define work elements that can be discussed
Use recognizable actions with consistent boundaries. Check whether an element can actually move to another operator. An inspection decision and its traceability record may need to remain linked even if the spreadsheet makes them easy to separate.
3. Record comparable times
Use a time study or another approved source and label the time basis. An observed average, a fastest cycle and an approved standard time mean different things. Keep ordinary work, unusual events and occasional activities distinguishable.
Machine processing can overlap manual work. When the chart represents operator workload, adding the full automatic machine time to manual work can double-count an interval. Use a standard work combination sheet to inspect the overlap.
4. Stack the elements and add the takt line
Use a consistent color for each element across operators. Keep the same vertical scale and unit for every bar. Retain the observed range or frequency of long cycles beside the chart so that the average does not conceal variation.
5. Make a revised allocation and test it
Check the required skills, tools, fixture positions, walking route and responsibility for each proposed transfer. Include new travel and handover time. Trial the proposal and re-measure quality, workload and output before adopting it.
Worked example: moving a six-second recording task
The following model assumes a 60-second takt and three operators. The times describe distinct assignments without double-counting overlapping intervals.
Operator | Current work content | Current total | Proposed total |
|---|---|---|---|
A | Part check 12 s, fixture set 18 s, fastening 18 s | 48 s | 48 s |
B | Assembly 24 s, fastening 24 s, inspection 12 s, recording 6 s | 66 s | 60 s |
C | Final check 24 s, transfer 18 s | 42 s | 48 s |
Moving the six-second record from B to C changes the allocation from 48/66/42 to 48/60/48 seconds. Total work content remains 156 seconds. This is a proposal, not a verified improvement result.
Before transferring the record, confirm that C can access the correct inspection result and associate it with the correct unit. If the handover adds five seconds of travel, include that time in the revised chart. The visual balance alone does not justify the change.
The segment order in a stacked bar shows time composition. It does not necessarily show the chronological order of work. Use the approved sequence and a timeline when dependencies matter.
Creating the chart in Excel
Create one row per element and one column per operator. Enter zero where an operator does not perform that element. Keep the current allocation and proposed allocation as separate tables.
Insert a stacked column chart with operators as categories and elements as series.
Add an equal takt value for every operator as another series.
Use a combination chart with takt as a line on the same time scale.
Show the unit, time basis, product scope and measurement date. Use labels or a legend that remain understandable when printed in grayscale.

Checking line balance numerically
At a 60-second takt, three operators provide 180 operator-seconds per required unit. The ratio 156 ÷ (3 × 60) = 86.7% describes the workload allocation relative to that takt capacity in this model. It is not overall equipment effectiveness or proof of actual utilization.
The theoretical staffing lower bound is ceiling(156 ÷ 60) = 3. Dependencies, skills, travel and safety may prevent a theoretically sufficient allocation from working. Do not treat the calculation alone as a staffing instruction.
Common questions about yamazumi charts
Should all bars be exactly the same height?
No. Aim for a feasible method that meets demand and preserves quality and safety. Forcing every bar to the same height can create unnecessary transfers or leave insufficient room for variation.
Is this the same as a standard work combination sheet?
No. A yamazumi chart compares assigned work content across operators or stations. A combination sheet shows the timing and overlap of manual work, walking and machine operation within a sequence.
Related reading:
Takt Time vs. Cycle Time vs. Lead Time: Formulas and Examples
Standard Work Combination Sheet: Free Excel Template and How to Use It
Time Study in Manufacturing: Method, Example and Free Excel Template
Summary: balance the real work, then verify the method
Build the chart from defined elements and comparable times.
Check dependencies and overlapping machine work before reallocating tasks.
Include new travel and handover time and verify the proposal on the floor.
AI can help organize the video observations behind the chart so the team can spend more time testing practical changes.
Analyze work content before balancing with Ollo Factory
Ollo Factory can classify manufacturing work videos into defined categories and aggregate the time spent on each. Reviewers can use the video and time breakdown to investigate long elements and compare how the work is performed.
Its improvement suggestions and comparison analysis can support a discussion of task sequence and allocation. Validate each proposal against the actual equipment, quality conditions and operator workload before changing the standard method.

Product screen published on Ollo’s English website. It illustrates the feature, not the results of the fictional assembly example in this article. Explore Ollo Factory features.
About the author
K.Y. | Business Development Lead & Marketing, Ollo Inc.
K.Y. leads business development and marketing at Ollo Inc., an AI startup originating from the Matsuo Laboratory at the University of Tokyo and the developer of Ollo Factory, a work analysis AI for manufacturing.
After studying engineering and design at university, K.Y. joined a major automaker and worked on new electric-vehicle development, from design through factory production, including hands-on assembly-line training. K.Y. later worked in sales and marketing at a manufacturing startup.
Today, K.Y. helps manufacturing teams use AI to improve the way they work through Ollo Factory.
Back to articles
See how Ollo Factory can support your factory
Book a demo
• See the product in action
• Discuss your production needs
• Explore available plans
Book a demo

Request a brochure
• Customer stories
• Key features
• How to get started