Standard Work Combination Sheet: Free Excel Template and How to Use It

A standard work combination sheet, also called a standardized work combination table, puts manual work, walking and automatic machine operation on one timeline. It helps a manufacturing team check the sequence, see overlaps and understand where an operator waits.
This guide explains how to read and complete the sheet using a fictional automotive component assembly. Ollo’s free Excel macro-enabled template includes a completed training example. The example does not authorize an operator to leave equipment or change a production method.
- What the combination sheet is used for
- What is included in the free Excel template
- Prepare the information before drawing
- How to complete a standard work combination sheet
- 1. Identify the operation and mark takt
- 2. List elements in their actual sequence
- 3. Measure manual, machine and walking intervals
- 4. Draw start and finish positions on the common axis
- 5. Test a revised sequence and measure again
- Common mistakes when reading the timeline
- Combination sheet vs. other standardized work forms
- Summary: show overlap and validate a repeatable sequence
- Transfer analyzed steps and times into a template with Ollo Factory
What the combination sheet is used for
Adding manual and machine durations does not always give the cycle duration. If an operator prepares the next part while an automatic test runs, those activities overlap. A common timeline makes that relationship visible.
Use the sheet to investigate:
Whether the assigned sequence can repeat within the required pace.
Where manual work, walking and machine operation overlap or create waiting.
Whether an alternative sequence is feasible under approved conditions.
The sheet complements a work instruction and a layout drawing. It does not replace part identification, quality acceptance criteria or equipment safety requirements.
What is included in the free Excel template
⬇ Download the free standard work combination sheet template

The .xlsm workbook contains a blank combination sheet, a completed example and additional instructions. It includes fields for the operation, part, line, author, date, takt and element times. A button generates element bars from the entered data.
The completed file illustrates toy-truck assembly and handling. Its visible parts and steps differ from the automotive component example used to explain the method in this article. Treat both as learning material and replace them with the actual operation before production use.
Use a desktop Excel environment compatible with the workbook’s features and follow the organization’s macro policy. The chart-generation button requires macros; browser spreadsheet applications may not run it. Do not lower security settings to use a template.
Prepare the information before drawing
Define the applicable product, operator, equipment, fixture and measurement scope. Confirm the approved method and the quality and safety conditions. Then establish the cycle start and finish and the boundary for each work element.
Calculate takt from net available production time divided by required quantity for the same period. Measure manual, walking and machine durations separately. In this article, machine time means an automatic operation after the operator has started it, not every period when equipment is powered on.
How to complete a standard work combination sheet
1. Identify the operation and mark takt
Fill in the document header. Enter takt and locate it on the time axis. For a 60-second takt, the reference line shows the required interval for producing one unit under the stated demand and time definition.
2. List elements in their actual sequence
Include loading, starting the machine, walking, unloading, checking and recording where applicable. Use short action names that match the work instruction. Avoid hiding a necessary inspection in a broad label such as “finish work.”
3. Measure manual, machine and walking intervals
Record observable start and finish points and measure several cycles. Keep unusual events with a note rather than silently deleting them.
Manual: the operator’s hands-on work.
Machine: the equipment’s automatic run interval.
Walking: movement between the defined work locations.
These categories describe the timeline. They do not determine whether an activity adds customer value or is safe to combine with another activity.
4. Draw start and finish positions on the common axis
The supplied template uses solid bars for manual work, dashed lines for machine time and zigzag lines for walking. Check the workbook’s instructions and legend before interpreting the generated chart.
Suppose the operator loads a unit for 8 seconds and starts a 25-second automatic test at second 8. If permitted, the operator then walks for 4 seconds and prepares another part for 12 seconds. Those actions finish at second 24 while the test finishes at second 33. The remaining 9 seconds are a possible waiting interval, not automatically free time that can be reassigned.
The example assumes the machine can run without continuous attendance and that the next preparation does not interfere with the test. Verify those conditions rather than deriving permission from the chart.
5. Test a revised sequence and measure again
Check precedence, tool availability, fixture capacity, material presentation and the operator’s return point. Include additional walking and handovers. Confirm that the sequence can repeat, not merely complete one favorable cycle.
Review good output, inspection completion and physical workload after the trial. Update the approved instruction and training only after the revised method has been accepted.

Common mistakes when reading the timeline
A long automatic run is not necessarily usable capacity for another task. Monitoring, safe access or quality conditions may require the operator to remain available. A machine can also continue across the drawing’s cycle boundary, so check the transition into the next cycle.
Do not add overlapping manual and machine time to calculate a single elapsed total. Do not omit walking or machine start operations. Finally, fitting inside takt is only one requirement: a feasible standard also needs a repeatable sequence, acceptable workload and the necessary work-in-process conditions.
Combination sheet vs. other standardized work forms
A combination sheet shows timing and overlap. A standardized work chart shows movement and material locations in the layout. A process capacity sheet examines machine capacity. A yamazumi chart compares the work content assigned to different operators or stations.
Choose the form that answers the question and use them together where necessary. A balance chart alone does not show whether an operator reaches a machine before its automatic cycle ends.
Related reading:
Time Study in Manufacturing: Method, Example and Free Excel Template
Takt Time vs. Cycle Time vs. Lead Time: Formulas and Examples
Yamazumi Chart: How to Balance Work with a Manufacturing Example
Summary: show overlap and validate a repeatable sequence
Measure and distinguish manual work, walking and automatic machine operation.
Draw their intervals on one timeline and check the next-cycle transition.
Test changes against equipment, quality and safety conditions before release.
AI can reduce the manual work of extracting steps and durations from video. The final combination still needs to be checked against the actual operation.
Transfer analyzed steps and times into a template with Ollo Factory
Ollo Factory analyzes manufacturing work videos, classifies the sequence and calculates element durations. Existing Excel templates can be imported to support downloading the analysis in the format used by the team, including a standard work combination sheet.
This connects observation, documentation and improvement review. Verify the extracted boundaries and categories, then check overlapping intervals and operational constraints before approving the resulting sheet.

Product screen published on Ollo’s English website. It illustrates the feature, not the results of the fictional assembly example in this article. Explore Ollo Factory features.
About the author
K.Y. | Business Development Lead & Marketing, Ollo Inc.
K.Y. leads business development and marketing at Ollo Inc., an AI startup originating from the Matsuo Laboratory at the University of Tokyo and the developer of Ollo Factory, a work analysis AI for manufacturing.
After studying engineering and design at university, K.Y. joined a major automaker and worked on new electric-vehicle development, from design through factory production, including hands-on assembly-line training. K.Y. later worked in sales and marketing at a manufacturing startup.
Today, K.Y. helps manufacturing teams use AI to improve the way they work through Ollo Factory.
Back to articles
See how Ollo Factory can support your factory
Book a demo
• See the product in action
• Discuss your production needs
• Explore available plans
Book a demo

Request a brochure
• Customer stories
• Key features
• How to get started